The drawings say what was supposed to get built. The as-builts say what actually did.
No job goes exactly to plan. A footer moves to clear a pipe, a duct gets rerouted around a beam, a valve ends up four feet from where the sheet put it. As-built drawings capture those changes so the next person who opens a wall, digs a trench or pulls a permit isn’t working from fiction.
They’re also the set most likely to be lost. Here’s what goes in one, who keeps it, and how to keep a copy that’s still readable in twenty years.
What an As-Built Set Is
An as-built set is the construction drawings marked up to show the finished work. It’s built during the job, not after it.
- It starts as a field set. One full-size set stays on site as the as-built copy, and changes get redlined on it as they happen.
- Every change gets marked. Moved walls, rerouted pipe and conduit, changed elevations, substituted equipment, and anything buried: underground utilities, sleeves, cleanouts, stub-outs.
- It gets dimensioned to something permanent. A buried line marked “about here” is not much better than no mark at all. Tie it to a corner, a property line or a fixed point.
- It gets turned over at closeout. The GC collects the marked sets from the trades and hands them over with the rest of the closeout package.
The marked-up set is only as good as the habit behind it. A change that gets redlined the day it happens ends up on the as-builts. A change somebody plans to “add at the end” usually doesn’t.
As-Built Drawings vs. Record Drawings
The two terms get used interchangeably, and on a lot of jobs that’s fine. When a contract separates them, it usually means this:
| As-built drawings | Record drawings | |
|---|---|---|
| Made by | The contractor and trades | The architect or engineer |
| What they are | Field markups on the construction set | A clean set redrawn from those markups |
| Form | Redlined paper, sometimes scanned | A new CAD or PDF set |
| When | Kept up during construction | Produced after closeout |
Record drawings are only as accurate as the as-builts they’re drawn from. If the field set wasn’t kept up, the clean set just looks more official while being wrong.
Some permits require a certified version. In Florida, for example, a stormwater system permitted through a water management district has to be certified as built by a Florida-registered professional before the permit moves into its operation phase, on Form 62-330.310(1), As-Built Certification. That certification is the engineer’s job, not the print shop’s. Your engineer and your permit conditions tell you exactly what’s required on a given job.
Who Keeps the As-Builts
Everybody assumes somebody else has them.
- The owner should get a set at closeout, and is the one who’ll need it most: for the remodel, the addition, the insurance claim or the sale.
- The GC usually keeps a copy in the project file.
- The architect or engineer keeps the record drawings if they made them.
- The building department keeps what was submitted for the permit. That’s the permitted design, which may not match what got built.
Ten years later, the GC may have closed the project file, the architect may have retired, and the owner’s set is in a garage in a tube. The as-builts for a utility run under a slab often survive only on paper, in one copy. That’s exactly the set we see come across the counter for scanning.
How to Keep a Set That Lasts
Field sets are disposable. You’ll reprint them. The as-built set isn’t, so treat it differently.
1. Keep it full size. As-builts carry the smallest, most important information on the sheet: a redlined offset, a pipe size, an invert elevation. An 11×17 copy is fine for walking the job, but a reduced sheet no longer matches its scale note, and handwritten markups get hard to read at half size. Keep the original full size, Arch D for most plan sets. D Size Paper: ANSI D vs. Arch D covers which D you have.
2. Store it flat if you can. The Northeast Document Conservation Center’s guidance on oversized paper is the same thing archivists tell architects: flat in a drawer is best, rolled loosely around a tube is next, and fold lines are where old sheets wear through first. A Florida garage in August is the opposite of a flat file. How to Fold Blueprints covers when folding makes sense, and the record set isn’t one of those times.
3. Scan it before it’s the only copy. One flood, one move, one cleanout, and a paper-only set is gone. A large-format scan holds the whole sheet at full size, redlines included, and gives you a file to print from next time instead of handling the fragile original. Blueprint File Types Explained covers why a scan is a different kind of PDF than one exported from CAD, and what that means when you reprint it.
4. Label it clearly. Mark the cover sheet “AS-BUILT” with the closeout date and the address. When there are three sets in the same drawer, nobody should have to guess which one reflects the finished building.
5. Keep more than one copy, in more than one place. The file goes to the owner, the GC’s project folder, and wherever you keep things that need to outlast a hard drive. Paper and digital, not either-or.
When the Paper Is All You Have
A lot of what gets built on in Southwest Florida was drawn before anyone saved a file: the original plans for a 1980s house, the as-builts for a utility run under a slab, a survey folded into a property file for thirty years. When an addition, a remodel or a permit resubmittal needs those sheets, the paper set is it.
Bring it to the counter in Port Charlotte. We scan large-format originals, faded and damaged sets going back to the 1980s included, reprint them clean at full size or 11×17, and email you the scanned file at no charge. Next time, the reprint starts from the file, not the paper.
We reproduce the drawing. We don’t certify it or stamp it. If your project needs a certified as-built, that’s your engineer’s call, and if you need one in Southwest Florida, Creek Engineering is down the hall.
For new sets, upload at pblueprints.com, walk in at the Port Charlotte print room, or get it delivered to the job in Charlotte, Sarasota, DeSoto, or Lee counties. Most orders that reach us during business hours go out the same day.
Precision Blueprint Co. is a division of Creek Engineering.
FAQ
What are as-built drawings?
As-built drawings are the construction drawings marked up to show what was actually built, including every change made in the field: moved walls, rerouted utilities, changed elevations, substituted equipment. They’re kept up during construction and turned over at closeout.
What is the difference between as-built drawings and record drawings?
As-builts are the contractor’s field markups on the construction set. Record drawings are a clean set the architect or engineer produces from those markups after the job. Many people use the terms interchangeably; contracts that separate them usually mean it this way.
Who is responsible for as-built drawings?
The contractor and trades mark up the as-built set during construction and the GC turns it over at closeout. The architect or engineer produces record drawings if the contract calls for them. Certified as-builts required by a permit are signed by a licensed professional.
Who keeps the as-built drawings after construction?
The owner should get a set at closeout. The GC usually keeps a copy, and the architect or engineer keeps any record drawings. The building department keeps the permitted plans, which may not match what was built.
How should I store as-built drawings?
Full size, flat if possible, rolled loosely if not, and away from heat and humidity. Scan the set so you have a file to print from, and keep copies in more than one place.
Can you make a digital copy of old paper as-builts?
Yes. A large-format scanner captures the whole sheet at full size, redlines included, and the scan can be reprinted at full size or 11×17.